45 Days to Weigh In on Spain’s 250 MW eSAF Complex

Castilla y León has started the regional approval procedure for RIC Energy’s Compostilla Green complex in Cubillos del Sil, opening public information and an environmental impact assessment.

Compostilla II coal power station in Cubillos del Sil, León, Spain, in 2009 — the municipality where Compostilla Green is planned
Image Source: Wikimedia Commons / Silvia Alba (CC BY 2.0, cropped)

At a glance

Castilla y León has opened the approval procedure for Compostilla Green, a planned 250 MW electrolysis and eSAF complex in León, with 45 days of public information and an environmental assessment. The step starts a permitting procedure; it is not approval, an investment decision or construction.

Castilla y León’s regional government has opened the approval procedure for Compostilla Green, a planned complex in Cubillos del Sil, León, that would pair 250 MW of alkaline electrolysis with a plant making electricity-based sustainable aviation fuel (eSAF) from renewable hydrogen and biogenic carbon dioxide. The resolution, dated 25 September 2026 and published in the regional official bulletin (BOCYL) on 30 September, opens a 45-day public information period, which also serves as consultation for the project’s environmental impact assessment. The promoter is Perseus Power, S.L.

For fuel buyers, the practical question is when announced eSAF capacity becomes permitted and financed capacity. Compostilla Green already has public money behind it: in the first call of the hydrogen-valleys programme (H2 Valles) run by IDAE, Spain’s energy agency, it was the highest-scoring project proposed for aid, with €81.4 million allocated. This resolution starts a permitting procedure. It is not an approval, a final investment decision (FID) or the start of construction.

Perseus Power is the project company behind Compostilla Green, which the Madrid-based developer RIC Energy presents as its own project; Spanish company-registry filings list RIC Hidrógeno as Perseus Power’s sole shareholder. RIC Energy says the plant would produce about 60,000 tonnes of eSAF a year. Its published figures for total investment differ, so SAF Path is not reporting one.

A Proyecto Regional is a Castilla y León planning instrument for developments of regional interest. According to the resolution, it would set the land-use and urban-planning rules for the complex and enable its construction. If approved, it would carry a declaration of public utility and social interest and, where applicable, the occupation of the property and rights needed to build it. The region’s industry department issued a favourable report on processing the project on 26 February 2026.

Compostilla Green already has its grant. Permits are the next test.

The 45 days start the day after the last required notice appears in BOCYL and in a widely read newspaper. The complex is subject to an ordinary environmental impact assessment, handled within the regional procedure rather than separately. Documents are available at the regional government’s office in León and on its open-government portal.

The resolution also sets out the process. Biogenic CO2 (carbon dioxide of biological origin) is captured and purified. A reverse water-gas shift (RWGS) step reacts it with hydrogen to make carbon monoxide. Fischer-Tropsch synthesis then turns that carbon monoxide and hydrogen, known as synthesis gas, into liquid hydrocarbons, followed by final product conditioning. Associated works include underground power lines, a hydrogen pipeline between the installations, a CO2 pipeline, and water intake and discharge pipes. The resolution gives no figures for output, water use or grid capacity and does not name the CO2 source. IDAE’s award documents refer to accredited offtakers for the fuel but do not name them.

RIC Energy says it awarded preliminary front-end engineering design (pre-FEED) work to Técnicas Reunidas in November 2025. In May 2025, RIC Energy and Siemens signed a memorandum of understanding on technical and financial cooperation, with Compostilla Green as a particular focus.

The site lies in the El Bayo Ampliación industrial sector, which a regional plan reserves for large, high-technology industrial projects. The resolution says the complex would bring such industry to the El Bierzo district. Cubillos del Sil is also where Endesa operated the Compostilla II coal-fired power station; in 2020, Spain’s markets regulator, the CNMC, reviewed the proposed closure of its remaining three generating units.

What to watch next: confirmation of when the 45-day public clock starts, the environmental assessment and final approval of the regional project. After permits comes the commercial test of named offtakers, financing and an FID, the hurdle SAF Path examined in The eSAF Bankability Problem. Timing matters because the EU’s ReFuelEU Aviation regulation requires a minimum share of synthetic aviation fuel from 2030, the deadline behind The eSAF Bet.

Sources: BOCYL; IDAE; RIC Energy; Siemens; CNMC; BORME

More news

Alby e-SAF plant enters FEED

Alby PtX has awarded Técnicas Reunidas the FEED contract for a planned 66,000-tonne-a-year e-SAF plant in Sweden.

2 MIN READ

SIA signs binding Aether SAF contract

A binding three-year contract advances the earlier Singapore Airlines–Aether memorandum, naming Project Beacon and a total ceiling of 4,800 tonnes.

2 MIN READ